Frankfurt / Main:
Frankfurt Int’l Airport “Rhein-Main“ (FRA): Apron A-West, first construction stage

Disciplines

  • Airports

Companies

Dorsch International Consultants

Construction Sum

approx. € 6 million

Client

Fraport AG

Duration

From 2008 to 2009

Project Activities

  • Construction supervision
  • Cost control
  • Photographic documentation of the construction process
  • Verification and compiling of construction documentation

Contact

Dorsch International Consultants GmbH

München (Headquarters)
Landsberger Str. 368
80687 München
Germany

Phone: +49 89 5797-0
Fax: +49 89 5797-800
E-Mail: info@dorsch.de

View in maps

Description

New aprons (58,500 m²) in concrete (54,000 m²) and in asphalt (4,500 m²) will be constructed at the former area of Lufthansa (east of hangar 5/6) as part of the planned boarding gate A0.

The apron construction will be completed in 4 phases, consisting of:

  • Demolition of existing pavements
  • Dismantling of existing supply and disposal lines and diof dismantling of an existing de-icing system
  • New construction of supply and disposal lines
  • Construction of pavements

The construction works are close to the ongoing airport operations. A high level of security is therefore needed, especially in the interface area to the existing aprons.