Karak: Kempinski

This project aims to achieve more sustainable patterns of energy consumption and production through monitoring the performance of three solar energy plants. The contract entails the supervision of the Operation and Maintenance of three PV Plants: 5.0 MW PV Plant located in Judaideh, Karak Governatorate, Jordan and 2.1 MW PV Plant located in Sul, Karak Governatorate. The project ultimately contributes to the economic development of the area, through the expansion of infrastructure for supplying modern and sustainable energy services for commercial usage, along with reducing the carbon footprint of the tourism industry.
Leistungen
Wasser und Umwelt
Gesellschaften
Dorsch International Consultants
Auftraggeber
United Saudi Jordanian Hotels and Tourism Company
Projektleistungen
- Monitoring of the performance of the PV Plants against the following Key Performance Indicators:
- Energy Production
- Performance Ratio
- Availability
- Supervision of the Maintenance undertaken by the O&M Contractor