Oberhausen:CENTRO Oberhausen
Disciplines
- Buildings & Architecture
- Urban Infrastructure & Utilities
Companies
Dorsch International Consultants
Client
Neue Mitte Oberhausen Projektentwicklung GmbH & Co. KG
Duration
From 1991 to 1998Project Activities
- Traffic investigations including dimensioning of internal road network
- Conceptual planning for effective wastewater drainage system
- Advisory services during contracting, handling of requirements made by authorities and planning permission procedure
- Clearance of building site and foundations including:
- risk analysis
- monitoring of remediation and demolition work (with a value of approx. ‰ 51 million)
- contract management
- subsoil investigations
- design and supervision of static and dynamic pile loading tests
- design of piled foundations with approx. 10 000driven piles
- digital terrain and groundwater modelling
- Infrastructure development:
- preliminary investigation of all supply and disposal lines
- design of road network
- design of surface wastewater and rainwater disposal system
- plan approval for main collector as intermediate solution for wastewater collection
- Design of artificial surface waters including bridges.
Contact
Dorsch International Consultants GmbH
München (Headquarters)
80687 München
Germany
Phone: +49 89 5797-0
Fax: +49 89 5797-800
E-Mail: info@dorsch.de
Description
Dorsch was commissioned by a firm of international property developers with the design and supervision of an urban redevelopment scheme involving mixed commercial utilisation on a former industrial site (disused steelworks) near the centre of Oberhausen in the state of North-Rhine Westphalia. The first development phase embraces the following buildings and facilities: shopping mall on two levels with sales area of 70 000 sqm, walkway with adjacent multi-purpose development including a cinemax cinema, a concert hall with 10 000 seats, 8 multi-storey car parks with space for a total of 10 000 vehicles, a central square, artificial streams and ponds covering 13 000 sqm as well as the integration of the entire site into the surrounding urban infrastructure – except for the necessary construction of new by-pass roads and of a public transport link with halt inside the project area.
Among the particular difficulties encountered were:
- high water table
- stipulations concerning surface water drainage
- refilled, partially contaminated subsoil
- partial filling of artificial surface waters with rainwater